Claremore Daily Progress

Breaking News

Government

February 12, 2013

County E911 over budget

CLAREMORE — The Rogers County Commissioners approved bids Monday for the construction of the new E911 Center.

Originally, the project was proposed at the cost of $1.6 million, however the bid package now totals $1.8 million.
The commissioners will be paying approximately $260,000 of that cost and will be doing site work to save money.
Commissioner Mike Helm questioned the board as to the source of the extra funds.
Commissioner Dan DeLozier said the $260,000 will be paid from the E911 cash account that is designated for equipment purchases.
There is approximately $800,000 in that account at this time. 
The courthouse project is running under budget and any left over funds will be dedicated to the E911 Center, according DeLozier.
Helm asked if the City of Claremore has opted to join the new E911 Center.
E911 Director Janet Hamilton responded not at this time. However, she feels they will after the center is up and running.
Helm then posed a question to Assistant District Attorney David Iski asking if the county could request the City to pay for part of the additional expenses.
 Can the county take back some of the E911 funds that the city currently receives, Helm asked.
Iski said that the board could review the document in which that splits the E911 funds.
Hamilton quickly cautioned the board, explaining that if they reviewed the document they will find that it is based on a lower population than what currently exists in the city.
“If we lose this argument we can lose additional funding,” Hamilton said.
No action was taken on the matter. In other business, the commissioners voted to select Riggs, Abney, Neil, Turpen, Orbison and Lewis Inc. to serve as legal council for the E911 Trust Authority.
 

1
Text Only
Government
  • Local attorneys fight to eliminate judgment

    Claremore attorneys — Thomas H. Williams and Jack E. Gordon Jr. —   filed a petition Tuesday to vacate the $27.9 million judgment awarded to Material Service Corp. 

    April 18, 2014

  • Rogers County Water Dist. 16 receives grant

    Rogers County Rural Water District No. 16 received a $24,999 grant Tuesday to help finance expansion of the district’s water supply infrastructure.  

    April 18, 2014

  • Grand Jury recesses until June 24

    The multicounty grand jury charged with investigating accusations of misconduct by Rogers County officials recessed Thursday until June 24-26, saying it needed to hear from more witnesses before returning a finding in the matter.

    April 17, 2014

  • Rogers County audit cover Oversight committee organized

    Rogers County Commission Chairman Dan DeLozier, Dist. 1, held a meeting Friday with county officials  to discuss ways of addressing deficiencies found in the recent 2011 and 2012 county audit reports.

    April 13, 2014 1 Photo

  • New Share the Spirit President Commissioners to discuss audit information

    While no audit information was addressed during a regular Rogers County Commissioners meeting Monday, plans for an upcoming public hearing were mentioned.

    April 9, 2014 1 Photo

  • State of the County - Elected officials host town hall forum

    Several Rogers County elected officials met Tuesday night in Chelsea to address citizens during the first State of the County informal town hall meetings.

    March 13, 2014

  • Courthouse security discussions continue

    The Rogers County Commissioners will discuss courthouse security Monday continuing the debate regarding key card access to secure areas.

    March 9, 2014

  • County gives attorneys key card access

    Rogers County Commissioners set a $20 fee for attorneys Monday to access secure areas of the courthouse.

    February 25, 2014

  • Council tables stormwater exemption issue

    Before a standing-room only crowd, the Claremore City Council voted Monday to table an ordinance amending the new Stormwater System Service Charge.

    February 19, 2014

  • Bump repair closes Akin Road

    Rogers County District 1 will close Akin Road at 6:30 a.m. today until Friday to repair a bump in the roadway.

    February 19, 2014

Poll

Severe storm season is beginning. Do you have a storm readiness plan at home?

Yes
No
     View Results
Featured Ads
AP Video