July 21, 2013

Bridge work saves county $10,000

CLAREMORE —

Rogers County Commissioner Dan DeLozier completed stage one of a project to repair Claremore’s Happy Lake Bridge this week.
Tulsa Pier Drilling completed the foundation piers Thursday, allowing the roadway to open ahead of schedule and saving approximately $10,000 in taxpayer dollars.
Doug Watts, President of Tulsa Pier Drilling LLC, lowered the cost to Rogers County by re-evaluating the type of piers and actual soil conditions found during construction.
The original bid price was approximately $63,000. Four 28-inch diameter holes were drilled and 26-inch diameter steel pipe called casing was placed approximately 40 feet into the ground. An eight-foot long, 24-inch diameter rock socket was dug below the casing to support the bridge. Rebar cages were installed, concrete poured, and casing was removed to complete the bridge pier.
Watts and his team used a drill similar to the machine owned by Rogers County District 2.
Commissioner Mike Helm purchased the drill with FEMA funds for approximately $583,000, however it was not used for the District 1 project.
This type of drill work takes specialized skills and equipment, according to Watts.
DeLozier said Friday he is extremely satisfied with the work Watts and his team provided.
Tulsa Pier Drilling was able to complete the work ahead of schedule and under budget, he added.
Saving taxpayer money is always a top priority, according to DeLozier.
The project is anticipated to last a few more weeks with a few days of one-lane closures while the next stage of construction is complete.
“The bridge was in desperate need of repair,” DeLozier said.
DeLozier’s crew will be assisting in the completion of the project after bidding requirements on the bridge top have been completed.
Notification of road closures will be sent to area residents through the countywide emergency management system.

1
Text Only
Top Stories
  • bridge work continues Portion of 4180 Road remains closed for completion of bridge work
    A portion of 4180 Road will remain closed through at least Thursday as workers complete a bridge widening project on the south end of Claremore Lake.
     

    April 20, 2014 1 Photo

  • Rogers County Audit:
    A recent report issued by Oklahoma State Auditor Gary Jones documented Rogers County Clerk Robin Anderson solicited donations from several Rogers County vendors.
     

    April 20, 2014

  • Students paint mural Catoosa High School artists paint mural to instill respect, inspiration

    Catoosa High School students, Devin Jackson and Spencer Plumlee, recently put the finishing touches on a mural that took more than a year to complete. 

    April 18, 2014 1 Photo

  • Local attorneys fight to eliminate judgment

    Claremore attorneys — Thomas H. Williams and Jack E. Gordon Jr. —   filed a petition Tuesday to vacate the $27.9 million judgment awarded to Material Service Corp. 

    April 18, 2014

  • Rogers County Water Dist. 16 receives grant

    Rogers County Rural Water District No. 16 received a $24,999 grant Tuesday to help finance expansion of the district’s water supply infrastructure.  

    April 18, 2014

  • Grand Jury recesses until June 24

    The multicounty grand jury charged with investigating accusations of misconduct by Rogers County officials recessed Thursday until June 24-26, saying it needed to hear from more witnesses before returning a finding in the matter.

    April 17, 2014

  • Harps Food opens new store in Inola

    On April 23, Harps Food Stores will reach a new milestone in their company’s history with the opening of its 75th store. 

    April 17, 2014

  • helping children Tri-County CASA seeks additional volunteers as child abuse cases increase

    From 2010-2013, Oklahoma has seen an increase in children entering foster care. According to Oklahoma Department of Human Services reports, approximately 11,000 children are in state’s custody because of child abuse or neglect — 4,000 in the Tulsa area alone and more than 100 in Rogers County.

    April 17, 2014 1 Photo

  • Judge refuses to dismiss Grubowski in DA suit

    A judge has denied businessman Myron Grubowski's motion to remove him from the defamation lawsuit filed by District Attorney Janice Steidley against sponsors of last fall's unsuccessful citizens petition for a local grand jury investigation of her  office.

    April 17, 2014

  • Controversial schools chief attracts crowd of opponents

    The field of candidates running for state school superintendent is unusually large — a sign of broad interest in what observers say is sure to be a referendum on the incumbent, Dr. Janet Barresi.

    April 17, 2014